Project Description
This project included 21,315 SF of new warehouse storage area and loading docks, including additional restroom facilities, facility accessibility upgrades, and adding fire sprinkler systems throughout much of the existing facility.
Construction of this new warehouse facility addition included demolition of existing structures for the new warehouse, retaining walls and fill material to elevate the entire warehouse slab to a full 52” dock height. GeoPier drilled foundation system, CMU block exterior walls, structural steel/bar joist roof system, and built-up roof. Constraints included constructing the new warehouse in the middle of a facility that runs 24 hours per day, without significantly impacting their ability to operate, with an operating conveyor structure running over/through the new building.